Pile Lifting Device for swift installation of 10.000 meters of steel foundation piles
2019-08-21    by : Arjen
  • Pile Lifting Device  for swift installation of 10.000 meters of steel foundation piles
  • Pile Lifting Device  for swift installation of 10.000 meters of steel foundation piles
  • Pile Lifting Device  for swift installation of 10.000 meters of steel foundation piles

The start of the construction at Jungong Road Elevated highway last week is another step in marking the success of prefabricated highway construction and steel foundations first introduced by Shanghai Chengtou Group at Shanghai’s Jiamin Highway.


DSC04195.jpg


Jungong Road will see 1531 steel foundation piles with a total length of 100.000m installed. This is the biggest scale of steel foundation implementation so far. The elevated highway will run along subterranean gas and utility lines and in most places the width of the construction site is a mere 16 meters. So what else is new at this project? Shanghai Urban Construction and Municipal Engineering Group has divided the 60m long piles into two sections, which means upending and positioning the ICE 50RF hammer on the 700mm diameter pile is quite challenging. The Pile Lifting Device allows the project team to ensure quick positioning of the hammer on the pile. The Pile Lifting Device upends the pile and then lifts it into the clamps, this means positioning is a fluid motion, no time is lost in positioning the hammer and lowering it until it clamps around the pile rim.


IMG_4811.jpg


In the following photo series, you can see how the Pile Lifting Device works.

Two holes are cut near the top of the steel casing




retractable lifting hooks are chained into the holes. 




DSC04173.jpg


The chains are connected to the Pile Lifting Device’s winch. The winch is powered by the ICE 1600 power pack and controlled by remote control. When the chain is pulled the pile moves into the clamp jaws.


The Pile Lifting Device is especially recommended for long piles with narrow diameters.


What are the advantages of steel foundations driven by ICE RF piling hammers?

·       Resonance free installation of your foundation close to metro, pipelines and buildings.

·       High frequency, low amplitude piling method that liquifies the soil just around the pile’s tip and surface to allow the pile to be driven into soils with N value of up to 50.

·       Low environmental impact, no soil excavation, bentonite and concrete required.

·       Rapid installation speed with only a crane, hammer and welding equipment needed

·       Steel piles offer guaranteed foundation integrity


DSC04196.jpg


We have reported extensively about this foundation method, if you are new to the technology you can read some articles here and here.


FAQ:

Why doesn't ICE design smaller clamps? The ICE 50RF is compact but very powerful, the clamps transfer the full 290t eccentric force of the hammer to the pile and require a clamping force that exceeds the ICE 50RF’s eccentric force with a safety factor of 1.2. The 175TC clamp set gives 350t clamping force and is therefore the best choice for the job.


Its busy in Shanghai now, steel foundations projects currently under construction are:

Beiheng Corridor

Jiyang Road

Jungong Road

Longdong Avenue

Service is not our promise, it’s our commitment!


Department Manager Mr. Fan is on site to advise the client on the correct length of the Pile Lifting Device chains. Our local team services an installed base of over 150 hammers. ICE users are in professional hands.


DSC04155 - Copy.jpg


Questions that
need to be answered?
I would be happy to answer them personally to you
Jim
Senior Sales Manager
Ask your question
021-34688990
  • Shanghai ICE Construction Machinery
  • Phone: (86) 21 3468 8990
  • Fax:  (86) 21 3468 8901
  • Email: contact@icevibro.com
  • Website: www.icevibro.com
  • Address: 6999 ChuanSha Road,
  •      PuDong District,No.B8,
  •      201202 Shanghai,China

沪公网安备 31011502008669号


沪ICP备19006476号