PROJECTS
Steel foundations for Shanghai’s Longyang Road Overpass
2021-04-28    by : Arjen
  • Steel foundations for Shanghai’s Longyang Road Overpass

This week we return to a typical ICE application in China: steel foundation piles for elevated highways.


Shanghai Jianshi’s working set-up at Longyang Road Overpass with 28RF 50RF


 I went to have a look at Shanghai Jianshi’s working set-up at Longyang Road Overpass  and discovered a job site where all the resonance free hammer’s strong points were demonstrated.

·       No resonance damage to existing elevated highways and electricity lines

·       No soil displacement by the installed piles

·       Quick mobilization and demobilization 

·       No need for trucking in and out of excavated soil, bentonite, concrete, or steel rebar.


Shanghai Longyang Road elevated highway flyover steel pile installation


Shanghai Longyang Road elevated highway flyover steel pile installation with ICE 28RF


The construction site is inside an existing ring of flyovers and cut in half by a bicycle tunnel and a three-lane dual carriage road. The construction site is thus divided up in 4 separate working areas. 


50RF at Shanghai Longyang Road elevated highway flyover steel pile installation


The access to the working areas is confined and this limited the choice of piling equipment and the length of the pile sections. The foundation design is for 700mm diameter 50m long steel friction foundation piles.


welding steel foundation pile sections together for Shanghai Longyang road elevated highway foundations


The 50m long piles were divided in 10m sections, shorter than usual, and the contractor chose to work with mobile cranes instead of a crawler crane. Each successive 10m pile section is securely welded to the previous after that has been driven into the soil. Electric power lines ran within a meter of the piling location and were unaffected by the piling work.


ICE 1600 power pack provides hydraulic flow for the 50RF which is pictured in the background


The client brought two sets of Resonance Free hammers. The first three sections driven by medium sized ICE 28RF and the last 2 sections with the large sized ICE 50RF. Using the two hammers on one project gives higher overall fuel economy and allows the project to be complicated within a shorter time.


mobile truck crane works safely with resonance free variable moment vibratory hammer


If you are considering steel friction piles for your project do not hesitate to get in touch with the specialists at ICE. We can put you in touch with all the resources you need to be off to a good start!


Shanghai ICE service team van is on site to provide maintenance service





Questions that
need to be answered?
I would be happy to answer them personally to you
Julie Zhao
Sales Support Manager
Ask your question
021-34688990
  • Shanghai ICE Construction Machinery
  • Phone: (86) 21 3468 8990
  • Fax:  (86) 21 3468 8901
  • Email: contact@icevibro.com
  • Website: www.icevibro.com
  • Address: 6999 ChuanSha Road,
  •      PuDong District,No.B8,
  •      201202 Shanghai,China

沪公网安备 31011502008669号


沪ICP备19006476号